Services
Water Well Construction
Well Development
The average water well in the foothills surrounding the Santa Clara Valley is a 10-inch bore with 5-inch PVC casing to a depth of 300 feet that will yield 10 to 20 Gallons Per Minute (GPM). The casing is a 5-inch diameter PVC-F480, SDR21 well casing, the “screened” casings are factory perforated with a .032” slot size. We typically install 20 feet of screen per 100 feet of cased well, with a cap on the bottom of the well. A gravel pack is deposited into the annular space between the earth and the casing, from the bottom of the borehole to within fifty-five feet of the surface. A sanitary surface seal consisting of bentonite grout or sand-slurry cement is then pressure pumped from the top of the gravel pack to the surface of the well (as per County requirements, the depth of the seal will vary in different geologic zones).
A common misconception is that bigger is better when determining the size of the well casing. Customers are often led to believe that a larger diameter casing will mean that their well will yield more water. Consider this, a 5-inch water well may produce up to 90 GPM if Mother Nature can supply the water. Therefore, a larger diameter casing will not supply more water, just more storage. Additional well screens and sand pack is not typically necessary but is recommended for certain locations and circumstances.
Our water wells are constructed according to the California Well Standards and the specifications set forth by the customer, Guardino Well Drilling and the local governing agency. All wells are chlorinated after completion of drilling in order to disinfect the casing and gravel pack. When your well is complete it will be ready for pump installation. All the necessary information concerning your well will be contained on the Water Well Completion Report to be issued upon receipt of payment.
Water Well Construction
Well Location
At least 100 feet from any existing or potential septic tank, leach field and/or pit privy and 50’ from sewer laterals
100’ from livestock area: corrals, pens, dog-runs, barns, etc. At minimum of 50 feet from any creek and/or tributary
In a location where drill cuttings will not flow onto a neighbor’s property, or into any storm drains, creeks, tributaries and/or conduits to waterways
At least 12 feet away from any overhead electrical wiring
Away from underground utilities: telephone, gas, water, electrical, etc.
Away from the drip line of a tree, slides or “geologic intersections”
Property Lines, Easements & Choosing the Spot
It is the customer’s responsibility to check for easements and underground pipelines. We usually recommend that the well is placed at least ten feet from the customer’s property line to provide for future access. The exact location of the water well will be chosen by the customer. Guardino Well Drilling will offer suggestions as to where to place the well based on the topography of the land, neighboring wells, and known geologic conditions in the area. If requested Guardino Well Drilling will provide the customer with the names of local geologists who may be of assistance in locating a site for the water well.
We require a minimum 20’ x 40’ semi-level pad for our drilling equipment. The site must also be free from overhead trees and limbs and accessible for drill equipment, piping and maintenance. The road entering the site must be at least nine feet wide and have a clearance of fourteen feet for our equipment to enter the property, bridges entering the site will also be checked for weight capacities. We often tell customers that if a cement truck can get into the site, then so can we. You may also want to consider that the well will eventually require electricity and piping and will need to be accessible for servicing in the future.
Depth
When determining the depth to drill and/or complete the well, the following factors should be considered:
- Encounter (3) water producing strata (past 50’)
- Deeper than your neighbors
- Stop at blue clay or rock (in the valley)
- Until the geology does not change (in the mountains)
- Until oil-shale is encountered, oil-shale indicates the potential for gas and/or salt (in the mountains)
- Average depth in the valley is 250’, average depth in the mountains is 400’
Logging
Logging is the record of the geology encountered while drilling the water well. Logs are also used by geologist and engineers in the design phase of the well. Logging is generally taken in two forms; 1) A Drillers Log written by the driller 2) E-log which is performed after the borehole has been drilled.
- Drillers Log: Driller’s log of formations and/or water bearing strata encountered
- E-log: electric log of borehole which typically measures formations and salinity through the use of specialized tools.
Casing
Casing is the central structure to a water well placed inside the borehole and is the key component to a completed water well.
- The well will generally produce as much water as the earth will provide
- The casing determines the size of the pump:
- 5″ and 6″ casing will accommodate a 4” submersible pump: 5 – 90 Gallons Per Minute (GPM)
- 8″ casing will accommodate a 6” submersible pump: 50 – 200 GPM
- 10″ casing will accommodate an 8” submersible pump: 100 – 800 GPM
- Large diameter steel casing is used to accommodate turbine pumps
- 5” SDR21 PVCF480 is the norm for Santa Clara County
- 6” Casing allows for easier well development (upon completion)
- 4” – 4.5” Casings allows for a smaller borehole which equals less cuttings (for confined work areas)
- 8’, 10” and 12” casings for municipal and agricultural wells
- SDR17 casing should be used for depths greater than 700’
- PVC has been the preference for the past 20 years
- Certa-Lok PVC – no glue, very fast
- Engineering and geology may require steel, stainless steel, stabilizers, etc.
- Screens typically have a .032” – .040” slot size (factory)
- Casing is typically hung plumb and center during gravel pack installation
- Centralizers are used to keep casing centered in borehole
- Solid rock holes may only require casing at the surface
- Borehole is usually twice the size of the casing
- 20’ of screen per 100’ of cased well
- A cap is usually installed on the bottom of the casing
Filter Pack
The filter pack is the material deposited in the annular space between the borehole and the casing and is typically referred to as a “gravel pack” or “sand pack”. The filter pack is inserted via free fall or tremie pipe and serves two main purposes; 1) To filter water as it enters the well and 2) Suspend the sanitary surface seal.
Different types of filter packs include:
- Gravel envelope: 3/8” washed pea gravel (shale, gravels, cobbles, most areas)
- Mix envelope: 3/8” washed pea gravel blended with #3 Monterey sand (clay, Valley areas)
- Sand envelope: #3 Monterey sand (sandy areas)
- Formation packer: used in open hole applications to suspend the seal
- Engineering or geology may require different types of filter pack
Sanitary Surface Seal
All water wells constructed in the state of California must have a sanitary surface seal. The following pertains to Santa Clara County:
- Sealing depths are dictated by geographic zone
- Most areas require a minimum 50’ seal, some areas require a minimum 100’ seal
- In the Valley, the seal must be approved by the Santa Clara Valley Water District prior to installation and must extend through clay, past the minimum required depth
- In Perchlorate zones the proposed sealing depth must be submitted by a registered Geologist or licensed engineer and must be approved by the Santa Clara Valley Water District
- Bentonite slurry is used in Air and Mud Rotary boreholes or remote access well locations
- 10-sack sand slurry / neat cement is used in Mud Rotary wells
- Seal is pumped from top of gravel pack to the surface
- The contractor must give 24-hour notice and 2-hour notice the day of the inspection and have an inspector present
- The well must have a 2” annular seal between the casing and earth
Well Completion
During the final stages of water well installation the following items are typically performed by the contractor:
- Make sure sanitary seal is stable
- Airlift or air-jet well (removal of drilling mud)
- Bail and swab well
- Disinfect well
- Test pump well, 2.5 GPM minimum for Santa Clara County Department of Environmental Health building permit requirements
- Perform bacteriological and mineral lab analysis
- Construct a minimum 3’ x 3’ x 6” concrete wellhead pad (as per county code) reinforced with rebar and sloping away from wellhead
- Secure wellhead and install bumper posts if needed (to protect wellhead from vehicular damage)
- Water well completion report to be completed and filed by driller within 30 days of completion